Construction Updates
Construction Update 13
Construction Update 12
Construction Update 11
Construction Update 10
Construction Update 9
Construction Update 8
Construction Update 7
Construction Update 6
Construction Update 5
Construction Update 4
Construction Update 3
Construction Update 2
Construction Update 1
Overview
The 2022 program provides a pavement rehabilitation in the form of a reclamation on the following streets:
- Biscayne Avenue West between 130th Street West and the end of pavement, approximately 2,670 feet
- 126th Street West between Biscayne Avenue West and Bacardi Avenue West
- Danbury Way between McAndrews Road (CSAH 38) and the northerly City limit (at the cul-de-sac)
- Chinchilla Avenue between McAndrews Road (CSAH 38) and the southern cul-de-sac
- 127th Court West between Chinchilla Avenue and the cul-de-sac
This project will provide a new road surface and drainage improvements as necessary along each of these streets. The limits of construction proposed on these streets can be viewed on the project map.
Schedule
- Neighborhood Open House Meeting - October 28, 2021 at Rosemount Community Center
- Public Hearing on Improvements - November 16, 2021
- Public Improvement Hearing Presentation December 7, 2021
- Design Complete, Order Ad for Bids - January 31, 2022
- Open Bids - March 3, 2022
- Award Construction Contract - April 19, 2022
- Assessment Hearing on Improvements - May 17, 2022
- Assessment Roll
- Construction Start - May 9, 2022
- Construction Completion (Planned) - July 8, 2022
Project Contacts
Please contact one of the following people if you have questions about this project:
Tim Hanson, Senior Project Manager
WSB & Associates (Design Consultant)
(651) 286-8459
tim.hanson@wsbeng.com
Brian Erickson, City Engineer
(651) 322-2025
brian.erickson@ci.rosemount.mn.us